You've found a space. The rent works, the location is right, and the landlord wants an answer by Friday. Then the question comes up: will the changes you need for your business require a building permit?
For most tenant improvements in Calgary, the answer is yes. Some cosmetic work doesn't need one. But once you move walls, change systems or change how the space is used, you're into permit territory. Knowing which side your project falls on before you sign the lease protects your budget and your opening date.
What counts as a tenant improvement?
A tenant improvement (often called a TI, fit-out or leasehold improvement) is the work that turns a leased commercial space into one that suits your business. It can be as small as new paint and flooring, or as large as gutting a former retail unit to build a dental clinic.
The size of the job doesn't decide whether you need a permit. The type of work does.
Work that usually doesn't need a building permit
If the use of the space stays the same (office to office, retail to retail) and the work is purely cosmetic, the City of Calgary says you don't need a building permit. The City's own examples are painting and furniture:
- Painting and similar surface finishes
- Furniture, including movable shelving and displays
Anything beyond that, ask before you start. And check your lease: many landlords require written approval for any changes, permit or not.
Work that usually needs a building permit
The City of Calgary requires a building permit for any construction in a commercial space, including building, moving, repairing or removing walls, structural or not. That usually includes:
- New, moved or removed walls. Any change to the floor plan, including new offices, treatment rooms or a kitchen.
- Electrical changes. New circuits, a panel upgrade or added capacity for equipment. Electrical work also needs its own trade permit, pulled by a licensed contractor.
- Plumbing and gas. New sinks, washrooms, floor drains or gas lines, also covered by trade permits.
- Heating, ventilation and air conditioning. New or upgraded units, new ductwork, and any change to kitchen or ventilation equipment.
- Fire and life safety. Changes to sprinklers, fire alarms, exits or fire separations.
- Structural work. Openings in load-bearing walls, new mezzanines, or heavy equipment that adds load to the floor or roof.
- Accessibility. Changes that bring in barrier-free requirements under the building code (the National Building Code – 2023 Alberta Edition), such as accessible washrooms and entrances.
You can need a building permit even with no construction planned. The City lists two cases: you're the first tenant in a new building, or your business changes the space's building code classification or occupant load.
When the use of the space changes
This is the one that catches business owners off guard. If your business changes how the space is used (a retail store becoming a physio clinic, an office becoming a café), the approvals change too.
The City needs the right planning approval in place before it will issue your building permit. Most tenant improvements don't need a full development permit, but a change of use does need planning approval:
- Permitted change of use: about 5 business days.
- Discretionary change of use, or one that needs a relaxation of the rules: about 10 to 12 weeks, including a 21-day appeal period. Approval isn't guaranteed.
Some businesses also need Alberta Health Services to review the application. The City's examples include restaurants, daycares, hair and nail salons, massage centres and tattoo studios.
That's why the time to ask is before you sign, not after.
How long do permits take?
The City of Calgary's typical timeline for an interior renovation building permit is 21 to 49 days, depending on how complex the project is and how complete the application is. A minor tenant improvement with a complete application may be issued within 21 business days. If you need planning approval for a change of use, add that time on top. In Vista's experience, most tenant improvement permits come through in 4 to 8 weeks.
The practical lesson: build the permit time into your lease. If your rent starts before you can legally build, you're paying for a space you can't use. Ask your landlord about a fixturing period or rent-free period that covers both approvals and construction.
Who applies for the permit?
The building permit can be applied for by the contractor, designer, architect or owner. Trade permits for electrical, plumbing, gas and HVAC are pulled by the licensed trade contractors. Depending on the project, an architect or professional engineer may need to design the work and stamp the drawings.
Incomplete drawings are one of the most common reasons approvals slow down. Each round of revisions adds time.
How Vista handles permits
At Vista Builder, design, engineering, permits and construction sit under one contract. Our in-house team prepares the drawings, our licensed P.Eng stamps the engineering, and we manage the application with the City of Calgary. One project manager stays with your project from the first meeting to the final inspection.
You can also order permit drawings on their own if you already have a contractor.
Opening a clinic? Read our guide to clinic build-outs in Calgary, including the approvals to plan for first.
Before you sign, get the space checked
Our Free Pre-Lease Review is a no-obligation walk-through of the space before you sign. We check four things:
- Use: can this space legally become what you need?
- Capacity: are the existing electrical and mechanical services enough?
- Code exposure: occupancy, accessibility and permit triggers.
- Timeline: a realistic path to opening.